Customer Testimonials for Rademacher Industrial
“The final concrete pour for the slitter foundation occurred on
Tuesday June 2.
Final clean up and painting is completed and the foundation
is now ready for the slitter. Magic Steel would like to thank the
Rademacher team for all of their hard work during the entire installation
process.”
– G.H., Plant Manager,
Magic Steel, Decatur,
AL
“John, as usual, OUTSTANDING job by your team! Please
find pictures inserted
with this email. Thank you to all of you for your
efforts, especially Mike D for his
coordination and engineering support.”
– R.H., Vice
President Steel Processing,
MARINO\WARE Texas Facility, Pasadena, Texas
“I would also like to add that Clayton, Mike, Augustine and Kevin represented your organization well. They were professional and when possible maintained cleanliness, exercised high safety standards along with keeping us aware of their progress and needs. We are very pleased with their work and hope this team may serve us again here in Pasadena, Texas in the very near future. From our Team to yours… Thanks!”
– I.T.
Project Manager,
MARINO\WARE Texas Facility, Pasadena, Texas
“Jeff—I do want to take this opportunity to tell you that your company did a remarkable job. The coil pit looks great and I am especially pleased with the work that you did on the shear foundation modification. Thank you very much for the work that you and your crew did and please pass along my appreciation to your guys. A HEARTY THANK YOU FROM THE CATOOSA TEAM!”
– G.F.,
General Manager, Southwest Division,
Macsteel Service
CentersUSA, Bensalem, PA
“My name is T.J. and I am the Senior Project Manager for Steel Technologies, Inc. Steel Technologies is an intermediate steel processor with 14 facilities in 9 states and Mexico.
In 2005 we received ‘capital monies’ approval to add a tension leveler to our existing pickle line at our Ghent KY facility (3985 US 42 West, Ghent, KY 41045).
As part of that project, we hired Rademacher Industrial System (940 Martin Luther King Blvd., Farrell, PA 16121) to do civil engineering, concrete foundation work, mechanical installation, electrical installation and the hardware and software integration.
The contract amount of Rademacher’s scope of work within this project exceeded $1,200,000.
The schedule for this particular project was very critical because we were upgrading an existing line that was in full production (24 hours/day, 7 days/week). We came up with a very aggressive schedule to get this done. I am very pleased to say that Rademacher “stepped up to the plate” and completed their scope of work ahead of schedule. They also competed their work within the dollar amount that was originally quoted.
We have also used Rademacher on some smaller jobs that turned out on or ahead of schedule and on budget.
In my opinion, Rademacher is a well-managed company with talented employees. Their field supervisors and other on-site employees are safety conscious and they conduct themselves in a very professional manner.
Rademacher Industrial System will continue to be right at the top of the list of contractors that will be considered on future projects done by Steel Technologies.”
– T. J., Senior
Project Manager,
Steel Technologies, Ghent, KY
“Rademacher Industrial System, Inc. (940 Martin Luther King Jr. Blvd, Farrell, PA 16121) was contracted by The Worthington Steel Company to provide technical expertise, labor and project management for installation of a Stamco slitting and package line.
Rademacher’s scope included civil engineering, excavation, foundation construction and equipment installation. Upon completion, the line was turned over to Worthington Steel to commence startup of production. The contract amount for this project was $910,500.00. The project was performed at our Worthington Steel facility (1127 Dearborn Drive, Columbus, OH 43085).
The project was executed in a professional manner with frequent communication and coordination at both the work site and with Rademacher’s business office. The work area was cordoned off and normal operation of the facility continued throughout the project duration. The quality and timeliness of the work was as expected allowing the line to startup according to our schedule, as has been our experience on previous projects with Rademacher.
– G.K., Project Manager,